The contractor in charge of rebuilding Cambodia’s national railway has 
been cutting corners on the health and safety of its workers, according 
to a report published yesterday by the Asian Development Bank.
 
TSO-AS & Nawarath, a French-Thai joint venture, was reportedly 
found to have grossly violated health and safety requirements at 
workers’ camps along both the northern and southern rail lines.
The
 report details, among other infractions, the deep pits and quarries 
left behind by TSO 
workers as they dig soil and stone for use in other areas of a 
construction site. 
Those pits along the section of the project 
located between Sisophan and Poipet, “were very dangerous … especially 
to children, [who] can fall into the pit and die”, the report states.
The
 pits had steep slopes, to a depth of more than four metres, according 
to the report, and yet TSO had made no attempt to take preventative 
measures. 
Safety scandals
In
 late 2010, two children – a brother and sister aged 9 and 13 
respectively – drowned while fetching water from a pond on a Battambang 
resettlement site for families who previously lived along the railway, 
according to media reports. 
The Cambodian government-sanctioned 
site was reported to be without fresh running water.
Japanese 
engineering firm Nippon Koei Co Ltd, the 
supervising consultant hired by the Cambodian government to oversee the 
rehabilitation project, conducted its investigation in December after 
TSO-AS & Nawarath failed to submit a monthly environmental report in
 November. 
The report was filed to the Ministry of Public Works 
and Transportation and the ADB early this year.
The allegations 
against TSO come amid scandal over the Kingdom’s national railway. 
Questioning transparency
Australian
 logistics firm Toll Group, which 
holds a 30-year operational lease for the rail with Royal Group of 
Companies, last week informed the Cambodian government of its intention 
to suspend service as a result of significant delays in TSO’s 
reconstruction, the
 Post reported.
Site monitors found that the southern line 
between Phnom Penh and Sihanoukville port was 51.9 per cent complete as 
of December. 
The northern line, which is broken into two 
sections, was only 3 per cent complete from Phnom Penh to Sisophon and 
35.4 per cent complete from Sisophon to Poipet, on the Thai border.
Insiders
 have said that contractual issues between TSO and the Cambodian 
government have been a main reason for the delays. 
TSO country 
head for Cambodia Claude Petit, however, when reached early yesterday by
 phone shrugged off that speculation.
“In a project, there are 
always contractual issues,” he said. “I won’t say anything on that.”
Petit
 also rejected claims that the delays were out of proportion with what 
he said was a complex project, claiming there were “a lot of reasons” 
for the broken deadlines. 
He declined to offer specifics of 
those reasons, however, saying only “it seems to be a problem for Toll”.
When
 asked if Toll’s withdrawal as a result of the setbacks would prompt the
 project’s partners to call into question the integrity of TSO’s work, 
Petit said “let them do it”. 
Petit could not be reached 
yesterday evening for comment on the Nippon Koei report. 
Illuminating hazards
Nippon
 Koei’s report highlights a number of health and safety hazards present 
at TSO’s sites, namely insufficient sanitation facilities for workers 
and a lack of protective equipment.
The “Kampot station [has an] 
existing toilet in [an] old building, but TSO did not allow the workers 
to use it, the [wash closet] in station building was locked,” the report
 states.
TSO does not provide clean water to many of the camps, 
and workers either have to buy their own clean water for bathing and 
drinking, or use the unsanitary water sources available to them, the 
monitoring team found during their December inspections. 
The 
report states that workers along the southern line had not been provided
 with safety gloves or masks, but also infrequently wore the safety 
helmets and boots they had been issued to them.
Philip Bulmer, 
Nippon Koei deputy project manager for the southern line, declined to 
answer questions yesterday on what he said was a “confidential” report.
ADB
 officials could not immediately be reached for comment.

No comments:
Post a Comment